Hauling Permits

Hauling Permits

A separate haul permit shall be required whenever hauling in excess of 500 cubic yards of material in or out of a site. A haul route must be submitted and approved by the Engineering Department.

The fee for the hauling permit is $300.00 per permit, per haul.

Additional requirements as set forth by the Engineering Department shall be met.  